Mead Valley Water System Improvements Phase II

Mead Valley Water System Improvements Phase II 
Located along Oakwood Street, Carroll Street, Day Street, and Pinewood Street, in the area south of Cajalco Road.

Project Description:  The project will install over 3,000 feet of eight inch diameter pipeline that will help improve water pressure for the homes along Oakwood Street, Carroll Street, Day Street, and Pinewood Street, in the area south of Cajalco Road.  The project will see remote water meters relocated to the front of each property, and the new pipeline will connect to the existing water lines in the community of Mead Valley.  Relocation of the meters will increase water pressure and fire flow capacity for the community. 

Project Timeline: The project is ongoing and is anticipated to be completed in mid-2025.  

Project Purpose: Improves operational efficiency and increases water pressure and fire flow capacity for the community. 

Project Update: As of May 2025, water lines are being completed and on-site connections to the new system should take place in summer 2025.