Daily Road Improvement Project

Located off of Daily Road between Snellen Lane and Boudreau Lane.

Project Overview

Eastern Municipal Water District (EMWD) will begin construction on Daily Road to enhance the roadway conditions between Snellen Lane and Boudreau Lane.

Schedule

Start Date: Monday, November 3, 2025
Estimated Completion: Mid-November 2025'
Work Hours: Monday-Friday, 7:00 a.m.- 4:00 p.m.
Access Restored: After 4:00 p.m. each day and on weekends

You can view a map with project components here

Traffic Impacts

Daily Road will be closed between Snellen Lane and Boudreau Lane during construction hours. Access will be restored each evening after 4:00 p.m. and on weekends. EMWD encourages residents to plan travel accordingly and drive cautiously near work areas to ensure safety for both the community and construction crews.

Construction Details

This project will mix a Class 2 Base Material, a durable engineered mix of crushed rock and sand, with a soil binder to provide a stable foundation for the road.
Type: Engineered aggregate base material
Purpose: Provides stable foundation
Properties: Strong, durable, supports heavy traffic loads
Installation: Placed in layers and compacted

Daily Road Improvement Project Factsheet

Contact Information:
Nico Gonzalez
951-928-3777, ext. 4885