Located on Sky Canyon Drive from Borel Road to Murrieta Hot Springs Road and along Winchester Road.

Post

Project Description:  The project will install approximately 6,670 linear feet of 36-inch diameter sewer pipeline. The pipeline route is planned along Sky Canyon Drive from Borel Road to Murrieta Hot Springs Road and along Winchester Road in the unincorporated area of Murrieta, located in Riverside County.

Project Timeline:  The project began construction in April 2021 and is set to finish in the Fall of 2022. Expect traffic delays and lane closures during this time.

Project Purpose:  Increasing the sewer capacity to accommodate growth in French Valley.

Communities that the Sky Canyon Sewer Project will serve 

Project Update:

  • As of October 5, 2021:
    • Final paving, overlay, and striping have been completed on Sky Canyon Drive.
    • Crews will continue working on Sky Canyon Drive for the remainder of the month to complete final housekeeping items.
    • Construction for the remainder of the project has moved north cutting in front of Borel Road and will continue parallel to Winchester Road.
    • REMINDERS:
      • Any remaining traffic control is set in coordination with the County of Riverside; this includes street closures. 

 

Sky Canyon Sewer Project -- Fact Sheet