Skip to main content Skip to site navigation

Spec. 1404W Murrieta Road Transmission Pipeline

RFP Post
Department Construction
Category Closed
Publication/Issue Date 01/12/2021 8:00 AM
Close Date 02/09/2021 5:00 PM

Refer to the Notice Inviting Bid or Addenda for Important Dates

PREQUALIFIED GENERAL CONTRACTORS ELIGIBLE TO BID

E.J. Meyer Company

J.F. Shea Construction, Inc.

James W. Fowler

MNR Construction Inc.

Norstar Plumbing & Eng., Inc.

OHL USA, Inc. dba Group OHL N. America

Steve P. Rados, Inc.

W.A. Rasic Construction Company, Inc.

Weka, Inc.

ORIGINAL BID DOCUMENTS

NIB - Pre Bid Walk Thru Directions

Proposal Package

Specification

Construction Drawings

Appendix A - Approved Materials List

Appendix B - Geotechnical Investigation Report

Appendix C - Geotechnical Baseline Report

Appendix D - Potholing Data

Appendix E - Traffic Control Cenceptual Plans

Appendix F - Perris II Desalter Site Restoration

Appendix G - Easement Deed

Appendix H - Brakish Pipeline Design

Appendix I - As-Built References_Part 1

Appendix I - As-Built References_Part 2

Appendix I - As-built References_Part 3

Appendix I - As-Built References_Part 4

Appendix J - P2D-(Menifee) Geotech Rpt-Final

Appendix K - Mitigation Monitoring & Reporting Program

SITE VISIT WALK THROUGH SIGN-IN SHEET

ADDENDA/LETTER OF CLARIFICATION

Addendum 1

Riverside County Flood Control & Water Conservation District Encroachment Permit

Revised Standard Drawing 812 Trench backfill and Roadway Repair

PCC Paving and Gate Loop improvement drawings

 Delta 1 18-inch Bypass revision drawings

Appendix L Highline Conceptual Sketch

Exhibit A – Existing Sewer System Maximum Allowable Discharge Rates

Exhibit B – Existing Water System Valves for Shutdown During Connections

Exhibit C – Discharge to Sun City Ponds Conceptual Plan

Letter of Clarification No. 1

PROPOSAL RESULTS

Preliminary Bid Summary

Final Bid Summary

PROPOSAL PACKAGES

James W. Fowler Co

E.J. Meyer Company

Norstar Plumbing and Engineering, Inc.

Weka, Inc.

MNR Construction, Inc.

PROJECT INFO

Official Bid Publication Date posted on EMWD website: January 12, 2021

Bonding Estimate: $16 Million - $18 Million

Project Location: Menifee, CA

PLANHOLDER REGISTRATION:  If obtaining these documents online, please complete the Planholder Registration form to be placed on the official planholders list and receive notifications of addenda and/or letters of clarification issued (for this project). Bidders are responsible for ensuring that they have received any and all addenda. If you have any questions, please email pillowb@emwd.org.

PUBLIC WORKS CONTRACTOR REGISTRATION: Bidders (and their subcontractors listed on the Designation of Subcontractors List) must provide an extract (pdf) with bid showing active registration.  To obtain an extract go to: https://efiling.dir.ca.gov/PWCR/