Skip to main content Skip to site navigation

French Valley Recycled Water Pipeline Project – Phase II

Post

Project Description:  The project will install approximately 12,300 feet of recycled water pipeline.

Project Location:  The pipeline route is planned primarily along Pourroy Road from Brookfield Park to Sheffield Park.  The route also connects west on Skyview Road and goes southwest on Algarve Avenue to connect Susan La Vorgna Elementary School and Emerald Park to the system.  The pipeline route also has a small section of alignment along Benton Road, east of Pourroy Road.

Project Timeline:  The project is set to begin construction in Fall 2022 and is set to finish by Fall 2023.  Expect traffic delays, detours, side-street closures, lane closures, temporary no-street parking, and traffic flaggers during this time.

Project Purpose:  The project will allow Emerald Park, Brookfield Park, Susan La Vorgna Elementary School, and other Valley Wide Recreation and Park District facilities to use recycled water instead of potable water for landscaping irrigation purposes.

Project Update (as of September 19, 2023):

  • Progress To-Date:
    • The Phase II Project is approximately 99% complete.  Crews have finished up installing pipe throughout the project alignment.  Crews are now working on final housekeeping items prior to completing final paving activities.  Intermittent traffic control may be set-up where work is taking place.
  • Upcoming Project Activities:
    • Pourroy Road:
      • Final (major) activities have been completed.
      • Crews continue working on minimal, housekeeping items for the last few weeks of the project duration.
      • Final paving has been completed.
      • The community should expect activity the on Monday, September 18th and the week of September 25th.
        • The community may expect intermittent traffic control during this time.
      • Benton Road:
        • Final (major) activities have been completed.
        • Crews continue working on minimal, housekeeping items for the last few weeks of the project duration. 
        • Final paving has been completed.
        • The community should expect activity the on Monday, September 18th and the week of September 25th.
          • The community may expect intermittent traffic control during this time.
      • Skyview Road:
        • All activities have been completed.
      • Algarve Avenue:
        • All activities have been completed.
      • ​The community can expect:
        • Regular working hours to remain at 7:00 a.m. to 4:00 p.m.  During working hours, the community can expect traffic control to be in place.
          • Traffic control may include delays, detours, temporary side-street closures, lane closures, temporary no-street parking, and access to sidewalks and bike lanes may be temporarily unavailable. 
          • Some traffic control measures may be left in place overnight during the week.
          • Traffic control plans are reviewed and approved by the County of Riverside.​​
          • Access to homes and school will remain open; if the entrances are blocked off, please wait for a crew member to assist in proceeding with caution.
        • Temporary increase in noise, dust, and vibrations from construction work;
        • After each workday, crews will be leaving streets in a drivable state with final paving set to occur at the conclusion of the Project;
        • Large machinery used may be secured safely in the public right-of-way
          • Please be on the lookout and use caution for crew members traveling the area with large machinery as they make their way to and from the project site. 
             
  • Letters and fact sheets have been mailed out to impacted, surrounding communities.
  • Please note: due to supply chain issues, dates are tentative and subject to change.

 

Project Fact Sheet

Contact Information:
Alma Ramirez
Public Affairs Officer
951-928-3777, ext. 4370
ramireal@emwd.org

Sign up for project e-notifications