Construction Lead Time Requirements

Your process will begin with the New Business Development Department to obtain an Application for Service detailing all applicable fees, Financial Participation Charges, and deposit requirements. In order to provide you with an Application for Service the following items will need to be submitted:

Please allow 3 weeks for the Application for Service to be processed. You may call to schedule your preconstruction meeting 6-8 weeks after making the requested payment on the Application for Service. The four to five week period allows:

  • New Business to produce and distribute the required documentation to the involved departments;

  • Engineering Department to copy drawings onto District files;

  • Field Engineering to prepare documentation for Preconstruction meeting.

Additional Information:

You can find additional information about the Waste Discharge regulations in the following documents:

  • Ordinance 59.5: Regulations for Waste Discharge and Sewer Use (710k Acrobat pdf)

  • Resolution 3003 (47k Acrobat pdf)
    A resolution of the Board of Directors of Eastern Municipal Water District establishing maximum concentration levels of industrial wastewater, hauled domestic liquid waste, and conventional pollutants in accordance with sections 3.300 and 3.700 of Eastern Municipal Water District Ordinance 59.5

Top

 

 

 

 

 

| meet EMWD | water service | recycled water | conservationwater education | news & info |development svcs | doing business |

| home | site map | contact us |

Copyright © 2000-2007 Eastern Municipal Water District. All Rights Reserved.
Please address any comments about this web site to webmaster@emwd.org.
 
Site designed by tWrite, inc.