Example 2: Office Building
The facility is an office building with
125,675 sq. ft. of office space.
STEP 1:
TOTAL BASE UNIT
|
÷ |
BASE UNIT |
X |
EDU FACTOR |
= |
TOTAL EDUs TO BE ASSESSED |
125,675 SQ. FT. |
÷ |
1000 |
X |
.75 |
= |
94.25 |
STEP 2:
TOTAL EDUs |
X |
CURRET SFPC |
X |
TENANT
DISCOUNT |
= |
TOTAL Sewer FPC AMOUNT DUE |
94.25 |
X |
$3,550.00*/EDU |
X |
1 |
= |
$334,584.50 |
TOTAL SEWER FPC AMOUNT DUE |
$334,584.50 |
* For Current Sewer Financial Participation Charges refer to Fee Schedule
|